The insulating platforms are used as auxiliary safety equipment for indoor live working up to 20kV.
Insulating platform should pass visual inspection at least once in three months.
If there are mechanical damages, cracks, etc., the platform should be repaired. After repair, the platform should pass mechanical and electrical tests.