Completed projects by Contragent 35

Delivery of materials and electrical installation activities at the site: Implementation of WWTP engineering and supply collectors in Chirpan, Bulgaria

Project: "Implementation of Wastewater Treatment Plant (WWTP) engineering and supply collectors in the town of Chirpan, Bulgaria"

Contractor: GP Group AD

 

Contragent 35 EOOD was selected as a contractor and performed the following activities:

Delivery of materials and construction works on:

  • External power supply;
  • Internal electrical installations, main distribution switchboard and switchboards in buildings;
  • Site electrical installations, pipe-line network and site lighting;
  • Delivery and installation of Concrete Complete Transformer Substation.